Statement of work · Marlowe Kett Architects



Fennick Studios, Shoreham. RIBA Stages 3 and 4.



Scope, deliverables, programme and fees for spatial coordination and technical design of a 1,140 m² photography and film studio building.

Client

Fennick Studios Ltd



Issued

5 March 2027, rev A



Fee, this SOW

£150,255 plus VAT

Studio building with a sawtooth roof by the harbour

Summary of this statement of work



Stage 2 was signed off on 26 February 2027. This SOW covers the next two stages only. Stages 5 and 6 follow under a separate SOW once a contractor is appointed.



Parties and site



Architect: Marlowe Kett Architects Ltd, RIBA Chartered Practice.

Client: Fennick Studios Ltd.

Site: Plot 7, Basin Road South, Shoreham Port. 0.31 ha, flat, made ground over chalk, flood zone 2.

Scope and dates



In scope: RIBA Stage 3, Spatial Coordination, and Stage 4, Technical Design, including the planning application and tender documents.

Start: Monday 22 March 2027. Tender issue: Monday 13 December 2027.

Construction budget: £3.18m, 1,140 m² GIA.

Stage 3 fixes the building. Stage 4 makes it buildable.
SSttaaggee 33 ffiixxeess tthhee bbuuiillddiinngg.. SSttaaggee 44 mmaakkeess iitt bbuuiillddaabbllee..

Deliverables, by stage



Every deliverable is issued from one federated IFC model. Drawings are views of it, not separate files.



Stage 3: coordinated model

Architecture, structure and MEP federated at LOD 300. Clash detection weekly, zero hard clashes at stage sign-off.


Federated building model on a studio screen

Stage 3: daylight on the stages

North rooflights tested in a climate-based daylight model. Target: uniform diffuse light, no direct sun on either stage floor between 09:00 and 17:00.


Photography stage under north rooflights

Stage 3: archive environment

A 180 m² archive held at 16°C and 35 percent relative humidity, plus or minus 5. Passive mass first, plant sized for the remainder.


Climate-controlled archive with mobile shelving

Stage 4: technical package

Full specification in NBS Chorus, Building Regulations full plans submission and tender documents for a JCT Design and Build contract.


Technical drawing of the roof eaves junction

Delivery method



Oona Kett is project director and your single point of contact. Sam Marlowe leads technical design. Eight people in the practice, founded 2018.



Weekly coordination, Tuesdays

Design team in the federated model for one hour. Clash report and actions issued the same day.

Fortnightly client review

Forty-five minutes, model on screen. Decisions logged in the shared register within 24 hours.

Design freeze at Stage 3 end

Layout, structure grid and envelope fixed before the planning submission. Changes after that point go through change control.

Change control

Every change is priced in time and fee before work starts. Nothing proceeds on a verbal instruction.

Stage gates

Each stage closes with a signed stage report: model, cost check, carbon figure and risk register.

Programme



Stage 4 starts after planning consent, not before, so no fee is spent at risk. Assumes client comments within five working days of each issue.



DayWeekMonthQuarterSemesterYear
M3Mar
M4Apr
M5May
M6Jun
M7Jul
M8Aug
M9Sep
M10Oct
M11Nov
M12Dec
M1Jan
Spatial coordination, federated model
Daylight, energy and carbon studies
Planning application package
Planning submission
Adur District Council determination
Technical design and specification
Building Regulations full plans
Tender documents
Tender issue
Stage 3Mar 22 - May 1

Spatial coordination, federated model



Stage 3Apr 5 - May 15

Daylight, energy and carbon studies



Stage 34 - May 29

Planning application package



Planning1 - Jun 2

Planning submission



PlanningJun 1 - Sep 1

Adur District Council determination

Statutory 13 weeks for a major application.

Stage 4Sep 6 - Nov 27

Technical design and specification



Stage 41 - Nov 2

Building Regulations full plans



Stage 4Nov 15 - Dec 11

Tender documents



Stage 413 - Dec 14

Tender issue



Fees and payment schedule



In pounds sterling, plus VAT. Based on 10.5 percent of a £3.18m construction cost: Stage 3 at 20 percent and Stage 4 at 25 percent of the total fee. Invoiced monthly against progress.



This statement of work

Stage 3, Spatial Coordination

Total
$66780.00

Stage 3, Spatial Coordination

Item
Price
Quantity
Total

Federated model, LOD 300





$28460.00

Energy model and PHPP





$11920.00

Whole-life carbon assessment

RICS methodology, 2nd edition.



$9740.00

Planning application and D&A statement





$16660.00
Total
$66780.00

Stage 4, Technical Design

Total
$83475.00

Stage 4, Technical Design

Item
Price
Quantity
Total

Technical design package





$47315.00

Specification, NBS Chorus





$12860.00

Building Regulations full plans





$8940.00

Tender documents and analysis

JCT Design and Build 2024, up to four bidders.



$14360.00
Total
$83475.00





Subtotal
$150255.00
Total (before tax)
$150255.00
VAT (20%)
$30051.00
Total
$180306.00

Acceptance criteria



Each stage is complete when all four are met and you have signed the stage report.







Zero hard clashes



Navisworks clash report at stage end shows no unresolved hard clashes between architecture, structure and MEP.





Carbon under 350



Upfront embodied carbon, modules A1 to A5, at or below 350 kgCO2e per m² GIA, independently checked.





Stage light verified



Daylight model shows no direct sun on either stage floor from 09:00 to 17:00, all year.





Archive within band



Dynamic simulation holds the archive at 16°C and 35 percent RH, plus or minus 5, for 98 percent of hours.

Terms



This SOW sits under the RIBA Standard Professional Services Contract 2020 signed on 4 January 2027. Where they differ, the contract governs.



Exclusions and client appointments

Structural, MEP, acoustic and fire engineers, the cost consultant, flood risk assessment, ground investigation, party wall surveyor, and all planning and Building Control fees. Principal Designer under CDM 2015 can be added for £7,880.

Revisions and change control

Two rounds of client comments per stage are included. Changes after the Stage 3 design freeze are priced in writing before work starts, at director £165 and architect £110 per hour.

Planning risk

The site is in flood zone 2 and within the port's operational area, so the Environment Agency and the port authority will be consulted. We cannot guarantee consent. If refused, Stage 4 does not start and no Stage 4 fee is due.

Intellectual property and the model

We retain copyright. You receive a licence to use the drawings and the IFC model for this building, including future maintenance and alteration. Native model files are handed over at Stage 4 completion.

Suspension, termination and liability

Either party may terminate on 28 days' written notice; work done to that date is invoiced. Liability is capped at £2m, matching our professional indemnity cover.

Authorisation



Signature by an authorised director of Fennick Studios Ltd is required before Stage 3 starts. Valid until Friday 19 March 2027.



Prepared by



Oona Kett Director, Marlowe Kett Architects Ltd

Unit 4, 32 Upper St James's Street Brighton BN2 1JN oona@marlowekett.co.uk

For approval by



Rowan Achebe Managing Director, Fennick Studios Ltd

Questions on the SOW go to Oona directly. Stage 3 kickoff is held for Tuesday 23 March at the Basin Road site.

Sign here
En approuvant ce document, vous le signez électroniquement.

Sign this statement of work

By signing, Fennick Studios Ltd instructs RIBA Stages 3 and 4 as set out above for £150,255 plus VAT, starting Monday 22 March 2027. Stage 4 begins only after planning consent. The first invoice is issued on 30 April 2027.