Fenwick Adair Design





Workplace interiors proposal · Fenwick Adair Design



Two floors built to win cases.



Interior design for Halsted Pryor LLP's 62,400 sq ft move to Fulton Market, from programming to move-in on May 8, 2028.

Prepared for

Halsted Pryor LLP



Date

April 5, 2027



Design fee

$446,605

The brief as we heard it



Four floors into two, and nobody loses ground



140 lawyers move from four floors in the Loop to floors 31 and 32 of the new Fulton Market tower. Same headcount, half the stacking, open by May 8, 2028.



Your current lease ends June 30, 2028, so the date is fixed. Your RFP asked for a private office for every partner and fewer square feet overall. We think both are possible if trial prep stops living in borrowed conference rooms.

The real stake is recruiting. Associates now choose firms partly on the floor they will work on. If any of this is wrong, tell us before you read on.

A litigation floor is a war room with offices attached.

Twelve people, and every move-in on the date



Fenwick Adair Design, founded 2016 in West Town. Tessa Fenwick and Julian Adair lead every project themselves. Law and advisory firms are most of what we do.




0.0M sq ft



Workplace delivered



Since 2016, across Chicago, Milwaukee and Detroit.


0



Law firm floors



Litigation, arbitration and appellate practices, from 40 to 310 lawyers.


0



On-date move-ins



Out of 31. We plan backwards from your lease expiry and from the slowest supplier, not from the design calendar. That habit is the whole record.


0%



Less paper storage



Average file room reduction after our records audits.


0



People, two principals

Corliss Wade LLP, River North

118 lawyers moved from three floors to two. Every partner kept a private office. Rent down $1.14M a year from the first month.


Glass-fronted partner offices along a limestone corridor

Brannock Vail Partners, West Loop

A trial floor with six lockable war rooms, each wired for document review on day one. Booked 81 percent of working days in year one.


Trial war room with oxblood acoustic panels

Merrow Capital, Fulton Market

A client floor on level 22 of a new tower. Conference suite, café and boardroom in one sequence. Installed in nine working days.


Boardroom with a long stone table and skyline view

Kestner Haskell LLP, Milwaukee

File rooms cut by 64 percent after a records audit. The space went to a library and twelve quiet rooms.


Library and quiet room with oak shelving and oxblood chairs

The schedule is set by the slowest chair



Workstations take 12 to 16 weeks to make. Custom millwork takes 10. So we lock furniture before drawings are finished, and every phase below is sized to protect that order date.



Program, four weeks

Interviews with every practice group, a two-week badge and sensor study on your current floors, and a records audit. Output: a signed space program.

Concept, four weeks

Two test fits across floors 31 and 32. Your partners walk both in VR before anyone picks one.

Design development, six weeks

Finishes, lighting, acoustics and millwork resolved. Workstation and seating specified now, not later.

Construction documents, seven weeks

Full drawing set for permit and bid, coordinated with your MEP engineer and the base building team.

Procure, release by December 7

FF&E priced, approved and released on one date, tracked in a live dashboard your facilities team can see.

Install and move, three weeks

Furniture install, punch list, art and styling. Lawyers arrive Monday, May 8, 2028.

Managing partners say it better than we do



They told us in week two that our seating supplier could not hit the date. We switched in time and moved in on schedule with every chair in place.

Danielle Pruitt

Chief Operating Officer, Corliss Wade LLP

We dropped a floor and kept every partner office. The rent saving paid the design fee inside five months.

Owen Tolliver

Managing Partner, Brannock Vail Partners

The VR walkthrough settled a four-month argument about office sizes in one afternoon. Nobody has raised it since.

Priscila Garza

Director of Operations, Merrow Capital

Their records audit found 2,300 boxes we were paying to store and never opened. That room is now our library.

Henrik Sorensen

Executive Director, Kestner Haskell LLP

Our trial team had two jury verdicts prepped in the war rooms within the first quarter. They were booked solid before the art went up.

Simone Beaumont

Chief Administrative Officer, Ellison Quade LLP

The procurement dashboard meant I stopped chasing vendors by email. I could see every order, deposit and ship date on one screen.

Lena Ingram

Head of Workplace, Thornbury Danforth LLP

They pushed back on our glass-everywhere brief and specified acoustic glazing for the partner row. Speech privacy tested at STC 45. Clients notice.

Raymond Sutter

Partner, Bexley Kane LLP

Union install crews, a freight elevator shared with three tenants, and they still finished punch two days early.

Mireille Vasquez

Firm Administrator, Harlan Lindgren LLP

One fee for the design. Your furniture budget stays yours.



In US dollars. The design fee is fixed at $7.16 per sq ft across 62,400 sq ft, built from our rates: principal $285 an hour, senior designer $195, designer $150. FF&E goods are a separate budget, paid by you to vendors at net trade price.



Design fee

Fixed for the scope in this proposal, invoiced monthly against progress.

Interior design, programming to move-in

Total
$446605.00

Interior design, programming to move-in

Item
Price
Quantity
Total

Program and workplace study

Interviews, sensor study, records audit.



$38460.00

Concept and two test fits

Includes three VR review sessions.



$61920.00

Design development





$96740.00

Construction documents

Permit and bid set, both floors.



$118350.00

Permit and bid support





$22180.00

Construction administration

Weekly site visits over 19 weeks.



$71640.00

Project management

About 9 percent of fee.



$37315.00
Total
$446605.00

FF&E procurement and install

Optional. On a goods budget of $3.19M, plus a 10 percent contingency held by you.

Procurement services

Total
$270680.00

Procurement services

Item
Price
Quantity
Total

Procurement management

7.5 percent of goods value.



$238980.00

Install supervision and punch list





$18740.00

Art placement and styling

Two days, both floors.



$12960.00
Total
$270680.00





Total
$717285.00

December 7 is the date that matters



Miss the FF&E order release and lawyers arrive to empty floors. Everything before it is planned to land that date. Assumes consolidated partner feedback within five working days. Move-in Monday, May 8, 2028.



DayWeekMonthQuarterSemesterYear
M5May
M6Jun
M7Jul
M8Aug
M9Sep
M10Oct
M11Nov
M12Dec
M1Jan
M2Feb
M3Mar
M4Apr
M5May
Program and workplace study
Concept, two test fits in VR
Design development
Construction documents
City of Chicago permit review
FF&E specification, pricing and approval
FF&E order release
Manufacturing lead times
Fit-out by your general contractor
Install, punch list and styling
Design4 - May 28

Program and workplace study



Design1 - Jun 25

Concept, two test fits in VR



DesignJun 29 - Aug 6

Design development



DesignAug 10 - Sep 24

Construction documents



PermitSep 28 - Nov 19

City of Chicago permit review

Typically 6 to 8 weeks. Not in our control.

FF&ESep 28 - Dec 3

FF&E specification, pricing and approval

Budget signed off by your COO before release.

FF&E7 - Dec 8

FF&E order release



FF&EDec 8 - Mar 24

Manufacturing lead times

Workstations 12 to 16 weeks, upholstery 14, millwork 10. This bar sets the date.

BuildNov 29 - Apr 7

Fit-out by your general contractor



Move10 - Apr 28

Install, punch list and styling



The fine print, said plainly



What decides whether the fee and the May 8 date hold.



What is the FF&E budget, and who controls it?

Our estimate for furniture, fixtures and equipment is $3.05M to $3.32M for both floors, plus a 10 percent contingency that you hold. You buy at net trade price and pay vendors directly. Nothing is ordered without your COO's written approval.

What happens if we change an order after release?

Most manufacturers take a 50 percent deposit and start production within two weeks. Once production starts, the deposit is usually lost. We will tell you the cost of a change before you make it, every time.

What does the design fee not include?

MEP and structural engineering, AV and IT design, the general contractor, City of Chicago permit fees, moving company and base building charges. We brief and coordinate each consultant, and review their fees before you sign.

How many revisions are included?

Two rounds per phase. A change to the program after concept sign-off is a change order, priced in writing before we start it.

Site access and install constraints

We assume freight elevator access on nights and weekends for install, union labor as the building requires, and storage for 10 working days in a bonded warehouse within 15 miles.

Payment and photography

Invoiced monthly, net 30. We keep the right to photograph the finished floors, with no client names or documents in shot, and share images with you first.

Sign by April 30 and we start May 4



This proposal holds until Friday, April 30, 2027. Sign below and we book the first practice group interviews for the week of May 4. Julian Adair and Tessa Fenwick can walk floor 31 with you on Thursday, April 22, if you would rather talk first.



Prepared by



Tessa Fenwick Principal, Fenwick Adair Design

1847 West Hubbard Street, Suite 400 Chicago, IL 60622 tessa@fenwickadair.com

For approval by



Renata Kowalczyk Chief Operating Officer, Halsted Pryor LLP

rkowalczyk@halstedpryor.com

Sign here
By approving this document, you sign it electronically.

Appoint Fenwick Adair Design

By signing, you appoint Fenwick Adair Design for interior design of floors 31 and 32 at a fixed fee of $446,605, starting Tuesday, May 4, 2027, for move-in on Monday, May 8, 2028. FF&E procurement services are confirmed separately if you select them.